Planning
Can you build on land in Germany? Bebauungsplan checks
Which planning regime governs your parcel, what the plan's numbers really allow, and how to resolve the decisive planning question before committing to a full design.
On this page

The parcel and project determine buildability. A Bebauungsplan sets rules; § 34 or § 35 governs questions left open by a simple plan or where none exists. Seek a preliminary building ruling (Vorbescheid) when the answer decides the purchase.
- Development plan
- § 30 BauGBread the drawing and text together
- Built-up area
- § 34 BauGBthe immediate surroundings set the test
- Open countryside
- § 35 BauGBordinary homes are generally not privileged
- Vorbescheid
- Normally 7 yearsBrandenburg; 3-year exception explained below
§ 30 BauGB: binding development plan
- Where it applies
- An effective Bebauungsplan covers the parcel.
- What decides
- Plan text and map, including Baufenster and extent of use.
- Likely position
- Apply the plan and secure road access and necessary utilities (Erschließung).
§ 34 BauGB: built-up settlement
- Where it applies
- Built-up settlement; no plan, or a simple Bebauungsplan leaves the question open.
- What decides
- The project must meet all § 34 requirements explained below.
§ 35 BauGB: open countryside
- Where it applies
- The parcel is outside the built-up settlement.
- What decides
- Apply the two statutory § 35 routes.
- Likely position
- An ordinary standalone home is generally not privileged.
A simple plan leaves gaps to § 34 or § 35 under § 30(3) BauGB.
Step one: confirm the planning status in writing
| Office | Action | Result |
|---|---|---|
| Municipality | Confirm plan status and request the complete plan documents. | Rules applying to the parcel. |
| Building control | Resolve the decisive project question through a Vorbescheid. | Binding answer on the described project. |
| Notary | Have a withdrawal right or suspensive condition drafted. | Contract tied to the defined Vorbescheid outcome. |
The municipal Bauamt (planning office) explains planning status and intentions without issuing a binding decision.
Identify the parcel by Gemarkung (district), Flur (subdivision) and Flurstück (parcel number). Ask:
- Does a Bebauungsplan cover the parcel? If so, request the in-force Planzeichnung (drawing), Textteil (written provisions), Begründung (explanatory memorandum), amendments and Bekanntmachung (publication notice); see § 10 BauGB.
- Without a plan, is it § 34 built-up area or § 35 Außenbereich?
- Is a plan, amendment, Veränderungssperre or by-law under § 34(4) or § 35(6) in preparation?
- What use does the Flächennutzungsplan show?
Find the parcel in the Brandenburg cadastral viewer. For a binding answer, apply to the Landkreis or kreisfreie Stadt Bauaufsicht under § 75 BbgBO.
Inside a Bebauungsplan: drawing and text are binding
A Bebauungsplan is a municipal by-law. Its planning drawing and written provisions apply together:
- Drawing: locate the Baufenster and local traffic areas.
- Text: check use, scale, roof, planting, parking and surfaces.
- Plan type: a qualified plan under § 30(1) covers the core criteria; a simple plan leaves gaps to § 34 or § 35.
A compliant project with secured Erschließung is permissible in planning terms, subject to other laws. Check which historical BauNVO version applies; later rules do not automatically apply, as the official Hamburg guidance explains. A decision may be suspended under § 15 BauGB.
A Veränderungssperre can suspend a project while the municipality prepares its plan.
- Under § 17(1) BauGB, it normally ends after two years, including time since the first suspension under § 15(1).
- It may be extended by one year and, in special circumstances, by one further year; check the current by-law.
GRZ and GFZ limit ground and floor area
§ 16 BauNVO uses two ratios; the applicable plan values are binding:
- GRZ: plot coverage, including the items listed in § 19(4) BauNVO. An attached terrace generally counts with the main building; see Brandenburg guidance B 1.15.1.
- GFZ: floor area in full storeys divided by the relevant plot area; it is not living space. § 20 BauNVO sets the calculation.
The worked result assumes all 800 m² is the calculation area under § 19(3) BauNVO. Check the Bauland behind the Straßenbegrenzungslinie; if none is set, use the actual road boundary or the area specified in the plan.
Source: BauNVO §§ 16, 17, 19 and 20; orientation values for a general residential area; checked 15 October 2026
Setbacks: check the applicable minimum distance
Under § 6 Abs. 5 BbgBO, the setback depth is 0.4 times the wall height and at least three metres. For buildings in classes 1 and 2 with no more than three above-ground storeys, three metres suffices.
The setback lies on your plot as a rule. Check two exceptions:
- It may extend to the midpoint of an adjoining public road, green space or body of water.
- Use of private neighbouring land must be secured under public law. A new Baulast requires that owner's declaration under § 84 BbgBO.
Before buying, verify an existing entry or agree how it will be created.
No plan or a simple plan: § 34 or § 35
Where no plan governs the question, location in a built-up settlement or the Außenbereich decides the route.
| Location | Check and consequence |
|---|---|
| § 34 built-up area | Fit by use, scale, building pattern and the part of the plot to be built on. |
| § 35 Außenbereich | Ordinary homes are generally not privileged; other projects need individual assessment. |
- § 34 also requires secured Erschließung, healthy living and working conditions and no harm to the townscape.
- Under § 35(1), a privileged project requires sufficient Erschließung and no opposing public interests; under § 35(2), other projects need secured Erschließung and must not impair public interests.
The 150 m radius and 157 mapped buildings do not define the legal nähere Umgebung under § 34 BauGB.
The last plot in a row may be Außenbereich; a § 34(4) by-law may clarify or extend the boundary. If the parcel is outside it, read the guide on building under § 35 BauGB.
Deviations: Ausnahme and Befreiung compared
§ 31(1) and (2) BauGB distinguish a plan-authorised exception (Ausnahme) from an exemption from its provisions (Befreiung).
| Point | Ausnahme | Befreiung |
|---|---|---|
| When | The plan expressly provides for this type and extent of exception. | It must preserve the plan's basic planning concept and meet a statutory ground. |
| Effect of the plan | The plan already allows the departure. | Case-by-case decision despite departure from the plan. |
| What to show | The plan clause and compliance with its exception. | Statutory ground, planning concept and affected interests. |
The plan's basic planning concept is the planning rationale expressed in its provisions. The departure must remain within what the municipality intended, or would have intended had it known the reason; it cannot replace a plan amendment.
It also requires public-welfare reasons that necessitate it, a departure justifiable in urban-planning terms, or clearly unintended hardship, plus compatibility with public interests, taking neighbours' interests into account.
If the purchase depends on an exception or exemption, obtain a binding ruling before notarisation.
The Vorbescheid: a binding answer before purchase
A Vorbescheid binds building control on a separately decidable question.
Ask in German: Ist das im beigefügten Lageplan dargestellte Wohngebäude mit [Nutzung, Grundfläche, Geschossen, Höhe und Lage] auf dem Flurstück [Gemarkung, Flur, Flurstück] bauplanungsrechtlich zulässig?
This asks whether the house shown on the attached site plan is permissible under planning law; fill in its use, footprint, storeys, height, position and the parcel identifiers.
In Brandenburg it normally binds for seven years under § 73 Abs. 1 BbgBO; if it also binds other authorities, three years under § 75 Abs. 3 BbgBO.
Ask for a fee estimate before commissioning.
- Submit exact questions, a Lageplan and the necessary drawings and project description under BbgBauVorlV.
- A § 31(2) Befreiung has a separate Brandenburg fee of €200–€5,000 for each exemption under tariff 1.9.3 BbgBauGebO.
Time. Before applying, ask Bauaufsicht for a written processing-time estimate from receipt of complete documents and a list of anything missing.
Agree with the seller on a contractual deadline for the required Vorbescheid that includes a buffer beyond the estimate and rules for extending the deadline if the authority is late; ask the notary to draft the agreed terms.
| Item | Brandenburg |
|---|---|
| Office | Lower building-control authority |
| Cost | €97 for each hour or part of an hour |
| Binding period | Normally 7 years; 3 if other authorities are bound |
Budget separately for the building permit.
| Procedure | Rate and fee |
|---|---|
| Simplified procedure | 1.1% of assessable building value at least €100 |
| Standard procedure | 1.4% of assessable building value at least €100 |
| Worked example: simplified | 1.1% of €300,000 = €3,300 |
Source: Brandenburg building fee ordinance. The percentages cover issuance of the permit and apply to the assessable building value, not automatically to the house price.
Technical checks, deviations or exemptions, and third-party participation may incur separate fees; the worked example is therefore not a complete administrative budget.
Which approval procedure applies to your house
Outside Brandenburg, ask Bauaufsicht about state procedures, documents and fees. This Brandenburg overview applies until 31 December 2026:
| Procedure | When | Effect or route |
|---|---|---|
| Bauanzeige | Class 1 or 2 home compliant with § 30(1) or (2); Erschließung secured | Start 1 month after receipt unless stopped; right expires after 4 years |
| Simplified | Compliant class 1–3 home under § 30(1) or (2); Erschließung secured | On application under § 63 BbgBO |
| Full | Other permit-required projects | Application under § 64 BbgBO |
For permit applications, the authority confirms receipt and states within three weeks whether the documents are complete.
Under § 63(4) BbgBO, Brandenburg generally decides within three months after the application is complete. For good cause, the total period may be extended by up to two months.
If the applicable period passes without a decision, approval is deemed granted. This is separate from a Vorbescheid.
From 1 January 2027: the published BbgBO amendment (Articles 1 and 3(2)) changes procedures and deadlines:
- § 62: Genehmigungsfreistellung will replace Bauanzeige and can cover § 34 built-up areas if its conditions are met.
- §§ 63/64: The simplified procedure will apply to projects other than Sonderbauten, and the full procedure to Sonderbauten (special structures).
- Deadlines: The new deadlines are set out in § 72(2). Before applying, obtain written clarification from Bauaufsicht of the procedure, applicable version and any transitional rules for your application.
Municipal consent: separate clocks under §§ 36 and 36a
- Cases
- § 31(1) and (2), § 33, § 34(1), (2) and (3a), and § 35.
- Role
- The authority requests municipal agreement.
- Cases
- § 31(3), § 34(3b) and § 246e.
- Role
- Municipal consent is required.
Each period starts when the municipality receives the authority's request.
| Case | Period |
|---|---|
| Municipality (§ 36) | 2 months; agreement deemed granted if not refused |
| Municipality (§ 36a) | 3 months; consent deemed granted if not refused |
| Affected public (§ 36a(2)) | Up to 1 month for comments; consent period extends by the same time |
Special cases: draft plans and housing provisions
Buying while a plan is still being written: § 33
Under § 33(1) BauGB, the standard route during plan preparation requires:
- A resolution to prepare the plan has been made.
- Public and authority participation under § 3(2), § 4(2) and § 4a(2)–(4) has been carried out.
- The project is expected to comply with future provisions.
- The applicant accepts them in writing for itself and successors.
- Erschließung is secured.
Sections 33(2) and (3) allow earlier admission in specified cases; treat the draft as information. An existing plan may remain in force until its amendment takes effect on publication under § 10(3) BauGB.
Housing under § 31(3)
With municipal consent, an exemption under § 31(3) BauGB may cover one or several comparable cases if compatible with public interests, taking neighbours' interests into account. It is unavailable where significant additional environmental effects are expected.
§ 246e BauGB
Until 31 December 2030, § 246e BauGB can allow housing projects to depart from BauGB provisions or a plan, but there is no entitlement.
- Municipal consent under § 36a and compatibility with public and neighbours' interests are required.
- In the Außenbereich, the site must have a spatial relationship with land under § 30(1), § 30(2) or § 34.
- Ask whether the municipality uses this route and whether environmental assessment is required.
What to have before the notary appointment
- Dated municipal confirmation of the planning regime.
- Obtain the complete in-force plan set requested above, or confirmation that none applies.
- Answer on plan changes, any Veränderungssperre and § 34(4) or § 35(6) by-law.
- The Flächennutzungsplan entry for the area.
- Outside Bavaria, obtain current Grundbuch and Baulastenverzeichnis extracts for setback and access obligations.
- In Bavaria, where there is no Baulastenverzeichnis, obtain the current Grundbuch and Bauakte, including Abstandsflächenübernahmen and Stellplatzsicherungen; see the Nuremberg building-control FAQ.
- If the answer decides the purchase, a Vorbescheid on the decisive question.
What buildability is worth, in money
Use the Brandenburg averages below for budgeting; they do not establish a parcel's buildability.
| Land category | Price per m² |
|---|---|
| Plots ready for single-family homes: state average | €219 |
| Single-family-home plots: around Berlin | €318 |
| Single-family-home plots: wider metropolitan region | €111 |
| Agricultural: cropland | €1.17 |
| Agricultural: grassland | €0.87 |
| Forestry: forest | €0.71 |
Source: Brandenburg property market report 2025.
- Compare the price and official Bodenrichtwert development status at BORIS and the Gutachterausschüsse. Bauerwartungsland is not baureifes Land; neither permits your house.
Start from the parcel. Get its identity, planning context and risk flags in one report. Check a parcel.
How qualified, simple and project-based plans differ is explained in types of development plan.
Where to find the plan in force for your parcel, and what to do if it is not online, is covered in finding the development plan for a plot.
What the symbols, lines and numbers on the plan drawing mean is explained in how to read a German zoning plan.
What a WA, MI or GE zone allows by type of use, and which noise values apply there, is explained in German zoning types under the BauNVO.
Where these rules are written
- Planning: § 30, § 31, § 33, § 34, § 35 and § 36 BauGB; freezes under § 14 and § 15 BauGB.
- Extent of use: § 16, § 17, § 19 and § 20 BauNVO.
- Brandenburg procedures: Brandenburg Building Code.
- Brandenburg fees: Brandenburg building fee ordinance.
- Brandenburg maps and values: cadastral viewer, geoportal, BORIS land-value portal.
Checked 16 October 2026; general information. See also: due diligence, utilities, Baulasten and costs and taxes.
For the complete sequence from the property search to the deed and registration, read how to buy a house or land in Germany as a foreigner.