Planning law

Types of development plan in Germany: qualified, simple and project-based

For the planning-law test, a qualified development plan (section 30(1) of the Building Code, BauGB) or a project-based plan (section 30(2)) means your project is allowed if it does not contradict the plan and access (Erschließung) is secured; under a simple plan (section 30(3)), whatever the plan does not cover is judged under section 34 or 35. State building regulations and other public-law rules still apply in every case (section 29(2)), and a project-based plan is also tied to one scheme, one developer and a deadline: if it is missed, the municipality is expected to revoke the plan (section 12(6)).

On this page

A listing saying "Bebauungsplan vorhanden" (development plan exists) is not enough. The kind of plan decides which planning-law test applies to your project and whether you are tied to someone else's scheme.

Three kinds of plan, three tests

The municipality (Gemeinde) draws up land-use plans on its own responsibility (section 2(1) BauGB); the development plan (Bebauungsplan) is the binding one (section 1(2)) and is adopted as a by-law, a Satzung (section 10(1)). State building regulations apply on top in every case (section 29(2) BauGB).

Qualified plan: four elements as the minimum

A plan is qualified if, on its own or together with other building-law provisions, it fixes at least four things: type of use, intensity of use, buildable areas and local roads. They come from the list in section 9(1) BauGB, nos. 1, 2 and 11.

The section 34 "fits in" test does not apply here. Departures are possible as an exception the plan itself provides for, or as an exemption (section 31 BauGB). For building envelopes and plot ratios, see zoning and buildability check.

Simple plan: sections 34 or 35 fill the gaps

If even one element is missing, the plan is simple. What it fixes still binds; the rest follows section 34 in built-up areas or section 35 in the outer area (Außenbereich), under section 30(3). Take an older plan with only building lines along the street: it decides where the house stands, while in a built-up area its use depends on whether it fits in with the immediate surroundings (section 34(1)).

Outside a built-up area, section 35 governs the rest: projects that are not privileged may be approved case by case if they do not affect public interests and access is secured (section 35(2)). On built-up versus outer area, see building in the outer area.

Project-based plan: one project, a contract and a deadline

Section 12 BauGB governs the project-based plan. It applies when a developer (Vorhabenträger), such as an investor, meets all of these conditions:

  • It submits a plan for the project and infrastructure agreed with the municipality, the Vorhaben- und Erschließungsplan (project and infrastructure plan).
  • It is willing and able to carry it out.
  • It commits to doing so within a set deadline.
  • It commits to bearing the planning and infrastructure costs in full or in part.

These obligations go into the implementation contract (Durchführungsvertrag), signed before adoption. The municipality decides at its discretion whether to start the procedure (section 12(2)); nobody can claim a land-use plan, not even by contract (section 1(3)).

The project and infrastructure plan becomes part of the development plan. Within its area the municipality is not bound by the section 9 list or by the Land Use Ordinance, BauNVO (section 12(3)). If the development plan nonetheless fixes a general zone there, it must state that only projects the developer has committed to in the implementation contract are allowed (section 12(3a)).

Plots outside the project plan may be included (section 12(4)), but section 12(3) speaks of the project plan area, so for a plot at the edge ask which part it is in.

Rules that do not apply inside the project area

Section 12(3) sentence 2 switches these off there (headings from the BauGB table of contents):

  • Sections 14 to 18: development freezes and deferral of building applications
  • Sections 22 to 28: protection of tourist areas and the municipality's pre-emption rights
  • Sections 39 to 79: compensation rules and land readjustment (Umlegung)
  • Sections 127 to 135c: the road and infrastructure charge (Erschließungsbeitrag) and cost refunds for nature conservation measures

There is therefore no Erschließungsbeitrag under the Building Code there; the developer bears infrastructure costs in full or in part, and the purchase contract shows whether they are in your price. Charges under state law are outside section 12; see road development charge after purchase.

If the plan fixes land for public purposes there, expropriation under section 85(1) no. 1 remains possible (sentence 3). Pre-emption rights from other laws are not affected by section 12; see pre-emption rights and approvals.

If the developer does not build: section 12(6)

If the project and infrastructure plan is not carried out within the deadline, the municipality is expected ("soll") to revoke the plan, possibly in the simplified procedure (section 13(2) BauGB). Until then the plan stays in force.

The developer cannot claim anything from the municipality because of the revocation (section 12(6) sentence 2). Afterwards another plan, section 34 or section 35 applies, so in the outer area the right to build can disappear.

A new developer needs the municipality's consent, which may be refused only if facts suggest the deadline is at risk (section 12(5)).

Buying into a project-based plan

If you buy in such an area, planning law allows what does not contradict the plan made for the scheme, not any house you choose. Building something else needs a changed or new implementation contract (section 12(3a) sentence 2) and, if the plan itself does not fit, an amendment to the plan.

Read the project and infrastructure plan with the plan documents (step 1 under "How to tell which kind of plan you have"). Then:

  1. Ask about the deadline and obligations. Section 10(3) does not cover the contract. Before the notary appointment, ask the municipality (Bauamt or planning office) and the seller in writing for the deadline and any amendments. In the same letter, ask the municipality when it will reply and whether it charges a fee.
  2. Check progress on site. Are the road and utilities built? Visit, and ask the municipality in the same letter to confirm the state of the works.
  3. Protect yourself in the contract. Agree with the notary, before signing, what applies if the plan is revoked or infrastructure is not built, for example a withdrawal right. See notary process and closing.

The three kinds compared

On a phone, swipe the table sideways to see every column.

Types of development plan under section 30 BauGB
Type of planWhat it fixesPlanning-law test and obligationsCheck before buying
Qualified (s. 30(1))At least type and intensity of use, buildable areas, local roadsAllowed if the project does not contradict what the plan fixes and access is securedAll four elements, access, any exception or exemption needed
Simple (s. 30(3))Fewer than the four minimum elementsThe plan's rules, otherwise s. 34 or s. 35What the plan leaves open, built-up or outer area
Project-based (s. 30(2), s. 12)Project and infrastructure plan as part of it, not bound by s. 9 or the BauNVOAllowed if the project does not contradict the plan and access is secured. Developer: deadline and cost commitment in the implementation contract (s. 12(1))Contract deadline, progress on site, risk of revocation (s. 12(6))

Other labels: Angebotsplan, early plan, fast-track procedure

"Angebotsplan" (offer plan) is not a term of the Building Code; it means a plan open to any builder, so a qualified or simple one. An early plan (vorzeitiger Bebauungsplan) precedes the land-use plan (Flächennutzungsplan), allowed only for urgent reasons and if it will not stand in the way of the intended urban development (section 8(4) BauGB).

Plans for inner development, such as infill, may be drawn up in a fast-track procedure on the conditions of section 13a(1) BauGB, without an environmental assessment (section 13a(2) no. 1 with section 13(3)). The procedure does not change the kind of plan.

Section 13b no longer exists in its former form. Section 215a BauGB deals with procedures under section 13b as worded until the end of 22 June 2021 or of 31 December 2023:

  • Subsections 1 and 2: procedures formally started before the end of 31 December 2022 could be completed applying section 13a, and plans already made could be brought into force in a supplementary procedure to correct errors (section 214(4) BauGB), both subject to subsection 3 and with adoption by the end of 31 December 2024.
  • Subsection 3: the environmental assessment and the offsetting of harm to nature (section 13a(2) nos. 1 and 4) may be omitted only if the municipality, after a case-by-case screening, concludes that the plan is unlikely to have significant environmental effects that would have to be weighed in the planning decision or offset as harm to the appearance of the countryside or to the functioning of the natural environment. The authorities and other public bodies whose remit the plan may affect must be involved in the screening. If the procedure then continues without an environmental assessment, the municipality must announce this publicly with its main reasons.

If a plan was made under section 13b, ask the municipality whether and when it was adopted and announced again under section 215a.

Is the plan valid? Announcement and court review

A plan takes effect on its public announcement (section 10(3)). Before that, section 33 BauGB can allow a project under conditions, and a development freeze under section 14 can block one.

Within one year of the announcement, anyone who claims the plan violates their rights, and any public authority, can ask the higher administrative court (Oberverwaltungsgericht) for a review, the Normenkontrolle (section 47(1) no. 1 and (2) of the Code of Administrative Court Procedure, VwGO). An invalidity ruling binds everyone (section 47(5)).

Certain procedural, formal and weighing defects become irrelevant if nobody raises them in writing with the municipality within one year (section 215(1) BauGB). Other defects are not. If the announcement is under a year old, ask whether a review is pending.

How to tell which kind of plan you have

  1. Inspect the plan documents. Drawing, written provisions, explanatory statement, notice and amendments. The municipality must keep the plan and its explanatory statement open to anyone and give information on request; the notice says where (section 10(3)). Write to the Bauamt or planning office with the cadastral district (Gemarkung) and parcel number and ask whether the plan is online, when you can see it and what copies cost; times and charges come from the municipality.
  2. Look for the project and infrastructure plan. If it is part of the documents, the plan is project-based.
  3. Tick off the four elements. Type of use, intensity (plot ratio or storeys), building limits or lines, local roads. If one is missing and no other building-law provision supplies it, the plan is simple.
  4. Get a binding answer. File a preliminary building enquiry (Bauvoranfrage) with the building authority (Bauaufsicht); ask it beforehand for the form, fee and processing time. See building permit and pre-application.

How it looks in the report

The sample report for a plot in Brühl-Badorf, North Rhine-Westphalia, has one page on what the state register of land-use plans holds for the plot and its surroundings.

Page 19 of the Brühl-Badorf sample report: planning law at the plot, showing no development plan in the register and a list of nearby development plans
No development plan in the register, seven plans 67 to 194 m away and three more up to 311 m, none dated (source: ogc-api.nrw.de, Bauleitplanung NRW, read 9 November 2026). Page 19 of 112 of the public sample report dated 10 November 2026 (Brühl, Badorf district, parcel 2550), page 3 of the chapter PDF. Open this page in the sample.

The page lists plan numbers and names, not the kind of plan; that only shows in the municipality's documents. The building authority, not the register, decides whether section 34 or section 35 applies to the plot, as the page says.

Checklist to print

  • □ Tick off the four minimum elements of section 30(1) in the plan
  • □ Simple plan: get written confirmation of built-up or outer area
  • □ Project-based plan: read the project plan, ask for deadline and amendments
  • □ Agree with the notary what applies if the plan is revoked
  • □ Note the announcement date; if under a year old, ask about a court review
  • □ Plan under section 13b: ask about section 215a

More checks before the notary appointment: property due diligence checklist.

For your plot, the GrundCheck report lists the development and land-use plans the state publishes in its register, with distance and source, and marks missing data. It does not confirm the kind of plan or its validity; the municipality does. The land register and the register of building encumbrances are not included. Order a report for a plot.

Editorial team: GrundCheck. Checked: 12 November 2026.

Official sources, accessed 12 November 2026

Common questions

The listing says "rechtskräftiger Bebauungsplan". What does that mean?

It usually means the plan is in force, which it is from its public announcement (section 10(3) BauGB). For one year after that, an application for judicial review can still be made to the higher administrative court (section 47(2) VwGO).

Can I build a different house from the developer's in a project-based plan?

In planning law, a project is allowed if it does not contradict the project-based plan and access is secured (section 30(2) BauGB). Where the plan fixes a general zone, it must state that only projects the developer committed to in the implementation contract are allowed (section 12(3a) BauGB). The contract can be amended or replaced, but that is for the municipality and the developer to agree. State building regulations apply as well.

What if a simple plan only fixes the type of use?

The type of use follows the plan. Where the house may stand and how large it may be is judged under section 34 BauGB in a built-up area or section 35 in the outer area (section 30(3)).

Are plans under section 13b BauGB still being made?

No new procedures under section 13b in its former form are possible. Section 215a allowed procedures formally started before the end of 31 December 2022 to be completed, or plans already made to be brought into force in a supplementary procedure, in each case with adoption by the end of 31 December 2024 and on the conditions of section 215a(3) for omitting the environmental assessment. Ask the municipality whether that happened for your plan.

Keep reading

Check this on your own property

The GrundCheck report organises public sources, visible risks and open professional questions for the parcel you confirm.

Check a property

Limits of this service

This service provides an automated pre-purchase check only. It does not establish ownership, title, buildability, construction permissions or service connections. It does not replace legal advice, a survey, advice from a surveyor or engineer, or tax or investment advice. Coverage is available across Germany, with data differences between state services.