Land types
Buying or building a house in or next to a forest in Germany
In Baden-Württemberg, Saxony, Schleswig-Holstein, Mecklenburg-Vorpommern, Saarland and Thuringia, state law requires new buildings to stay 30 m from the forest, with exceptions from the building or forestry authority. A new house inside a forest also needs planning permission, usually under section 35 BauGB, and a forestry permit to convert the land.
On this page
A house inside a forest: two sets of rules at once
In German law, forest (Wald) is any land stocked with forest plants (section 2 BWaldG), including clear-felled patches, clearings, forest tracks and forest meadows. What grows there counts, not the wording of the land register or a listing. States may add land or exclude parkland belonging to a home.
A new house first needs planning permission. A wooded plot without a zoning plan and outside a built-up village is usually "outer area" (Außenbereich). Projects that serve a farm or forestry business and take up only a minor part of its land are privileged there (section 35(1) no. 1). A private home is an "other project": it may be approved case by case if it does not harm public interests and access and utilities are secured (section 35(2)).
Those interests include the land-use plan, nature conservation and the risk of scattered settlement (section 35(3)); see building in the outer area.
Forest law comes on top: clearing and converting forest needs a permit from the authority named by state law.
- 1. Planning permission?Outer area: a private home only if no public interests are harmed (s. 35(2) BauGB).
- 2. Conversion approved?Forestry permit, often with compensation (s. 9 BWaldG, state law).
- 3. Forest setback?BW, SN, SH, MV, SL, TH: 30 m or an exception. Elsewhere ask.
- 4. Access secured?Secured access under s. 35 BauGB, not just a forest track.
Source: Editorial schematic based on sections 2 and 9 BWaldG, section 35 BauGB and the state forest acts, 12 November 2026
A house next to a forest: the 30 m setback in six states
Building beside a forest needs no conversion, but six states require a gap; Mecklenburg-Vorpommern names the reason: danger from windthrow (trees blown over) or forest fire. The table shows what each rule covers.
- 30 m: forest setback for new buildings in BW, SN, SH, MV, SL and TH, with exceptions under state law.
- 50 m: Brandenburg bans fires in the forest and within 50 m of its edge. Those entitled to use a plot may light a fire on it from 30 m with fire precautions, but not at forest fire danger levels 4 and 5.
Source: Section 4(3) LBO BW, s. 25(3) SächsWaldG, s. 24 LWaldG SH, s. 20 LWaldG M-V, s. 14(3) LWaldG Saarland, s. 26(5) ThürWaldG, s. 23 LWaldG Brandenburg; state law portals, accessed 12 November 2026
On a phone, swipe the table sideways to see every column.
| State | Provision | Distance and what it covers | Exceptions in the act |
|---|---|---|---|
| Baden-Württemberg | Section 4(3) LBO | 30 m: structures with fireplaces or stoves to forest, moor, heath; buildings to forest | Not for buildings the zoning plan allows closer, nor for alterations or changes of use of lawfully existing structures. Exceptions possible, so are larger distances. |
| Saxony | Section 25(3) SächsWaldG | 30 m: same as Baden-Württemberg | Exceptions possible, so are larger distances; decided by the lower building authority after consulting the forestry authority. |
| Schleswig-Holstein | Section 24 LWaldG | Projects under s. 29 BauGB prohibited within 30 m | Not for projects exempt from permit and notification under s. 69 of the state building code or for public transport facilities, in both cases except buildings. The building authority may allow less, with forestry agreement, if no danger is to be feared. |
| Mecklenburg-Vorpommern | Section 20 LWaldG | 30 m when structures are erected | Exceptions by ordinance (not reviewed). Under s. 20(3) the exception decision may be omitted only if both apply: the structure complies with a legally binding zoning plan, and that plan was drawn up with the forestry authority taking part. Other requirements for the project are unaffected. |
| Saarland | Section 14(3) LWaldG | 30 m between forest edge and outer wall when buildings are erected; an extension must not shorten the distance | Forestry authority grants it if both apply: an easement accepting falling trees and waiving damages, and no increased risk of trees falling. |
| Thuringia | Section 26(5) ThürWaldG | 30 m when buildings are erected | Exception from the lower forestry authority, included in the building permit. |
| Bavaria, Berlin, Brandenburg, Hamburg, Hesse, Rhineland-Palatinate, Saxony-Anhalt | – | Not found in the state forest act; in Bavaria not in the building code (BayBO) either | Ask the building and lower forestry authorities; a distance may follow from the building code, a plan or an ordinance. |
| Bremen, Lower Saxony, North Rhine-Westphalia | – | Act not reviewed | Ask both authorities. |
Only Saarland says how to measure: from the forest edge to the outer wall. Have the lower forestry authority confirm where the forest edge lies before you pay.
Applying for an exception from the setback
- Find the right office. The table names it for Saxony, Schleswig-Holstein, Saarland and Thuringia. In Mecklenburg-Vorpommern the forestry authority decides, or the building authority in agreement with it where a building permit is needed. In Baden-Württemberg section 4 LBO names none, so ask the lower building authority at the district office (Landratsamt) or city.
- Documents. In Saarland the application needs a plan showing the parcel reference and the exact position of the building. You also need the easement in favour of the forest neighbour (see easements and rights of way), which only exists once agreed and entered in the land register (section 873 of the Civil Code, BGB). Elsewhere the deciding office tells you what it needs.
- Time. In Saarland the forestry authority checks completeness within 6 working days and decides within 3 months of a complete application; otherwise the exception counts as granted. In Thuringia forestry agreement counts as given unless refused within 2 months of the building authority's request. In Saxony consultation counts as done if the forestry authority stays silent past the building code deadline.
- Cost. The provisions quoted set no fee for the exception. Ask about the administrative fee; in Saarland add notary and land registry costs for the easement.
Buying a house that already stands in or by a forest
Mecklenburg-Vorpommern, Saarland and Thuringia apply the setback "when erecting" a building. Baden-Württemberg exempts alterations and changes of use of lawfully existing structures but names no replacement new build. Schleswig-Holstein's ban refers to projects under section 29(1) BauGB, which include building, altering and changing the use of structures.
In the outer area, section 35(4) BauGB helps certain projects: conflict with the land-use plan or a Landschaftsplan (nature plan), harm to the natural character of the countryside or the risk of scattered settlement cannot be held against them, provided they are otherwise compatible with the outer area. Three of the six cases matter most for an existing home:
- Replacement (no. 2): a new residential building of the same kind (gleichartig) on the same spot, on four conditions: the existing building was lawfully erected; it has deficiencies or defects; the owner uses it or has used it personally for a considerable time; and facts justify assuming that the new building will serve the own needs of the previous owner or their family. Where the owner inherited the building from a previous owner who had used it personally for a considerable time, facts pointing to the own needs of the owner or their family are enough. The act gives buyers no such relief, so ask the building authority before buying whether you would qualify.
- Rebuilding after destruction (no. 3): prompt rebuilding, on the same spot, of a lawfully erected building of the same kind destroyed by fire, natural events or other exceptional events.
- Extending a residential building to two homes at most (no. 5): the building was lawfully erected, the extension is reasonable in relation to the existing building and to housing needs, and where a further home is added, facts justify assuming that the previous owner or their family will use the building themselves.
In cases 2 and 3 the new building may be slightly larger than the one removed or destroyed and stand slightly off its position (section 35(4), third sentence). Larger extensions, a different kind of house or another site are not covered.
The forest setback and state forest law still apply. Ask the seller for the building file (Bauakte) and have the building authority confirm that the house exists lawfully and what it may be used for. A building permit missing from the seller's papers is an open question to settle with the authority before you buy. A permitted weekend house is not a permitted home, see tiny houses and weekend houses.
If the sale includes forestry land, the purchase itself may need approval under the Land Transactions Act (Grundstückverkehrsgesetz, sections 1 and 2 GrdstVG; in Baden-Württemberg section 1 ASVG); states may exempt plots up to a certain size, and section 4 lists further exceptions. Your notary checks whether your purchase is covered; see buying forest land.
Converting forest and replanting elsewhere
Section 9 BWaldG sets the frame: states may exempt conversion where another use has been fixed with legal effect, or restrict it and ban it in protective and recreation forest. Temporary conversion comes with a condition to replant.
Converting forest land: who approves under state law
- Baden-Württemberg: higher forestry authority (s. 9 LWaldG)
- Bavaria: lower forestry authority, clearance permit (Art. 9 and 39 BayWaldG)
- Berlin: competent authority; without a separate application the building permit includes it (s. 6 LWaldG)
- Brandenburg: lower forestry authority (s. 8 LWaldG)
- Hamburg: competent authority (s. 4 LWaldG)
- Hesse: permit required (s. 12 HWaldG)
- Mecklenburg-Vorpommern: forestry authorities, in advance (s. 15 LWaldG)
- Rhineland-Palatinate: forestry office (s. 14 LWaldG)
- Saarland: forestry authority (s. 8 LWaldG)
- Saxony: forestry authority (s. 8 SächsWaldG)
- Saxony-Anhalt: forestry authority (s. 8 LWaldG)
- Schleswig-Holstein: forestry authority, in advance (s. 9 LWaldG)
- Thuringia: lower forestry authority, in advance (s. 10 ThürWaldG)
- Bremen, Lower Saxony, North Rhine-Westphalia: not reviewed
There is no federal fee. Brandenburg requires the harm to be offset, for example by planting forest elsewhere, and charges a forest conservation levy, set by ordinance, where it cannot be offset; so does Saxony. In Saarland compensation is waived only for areas under 300 m². Ask for the figures for your plot in writing.
Forest on the ground, building land in the plan
A zoning plan showing housing on wooded land does not settle conversion automatically. Some states accept the plan under conditions:
- Brandenburg: a binding zoning plan under section 30 BauGB with another use counts as the permit if it sets the nature and forest compensation. If a building permit allows the other use, no separate conversion permit is needed.
- Berlin: a zoning plan under section 30(1) or (2) BauGB is enough if full forest compensation is set in it or agreed in an urban development contract.
- Mecklenburg-Vorpommern: no permit if a plan or bylaw provides another use, there was no forest when it was adopted and fewer than ten years have passed since.
- Schleswig-Holstein: forest that grew naturally on land legally set for another use needs no permit for ten years after that use took effect.
- Bavaria: no clearance permit where a bylaw or permit sets or allows the change of use; the refusal grounds of Art. 9 still apply there by analogy.
Elsewhere, ask the forestry authority whether the plan covers conversion; until it does, the plot is not ready to build on.
Fire and access at the forest edge
In Brandenburg, fires and smoking are banned in the forest and within 50 m of its edge (section 23 LWaldG); the drawing above shows the exception for your own plot.
Section 35 BauGB requires secured access in the outer area, and a forest track is not automatically a public road; see access and infrastructure.
How it looks in the report
The sample report for a parcel in Brühl-Badorf maps how far away the nearest mapped woodland is.

The 74 m is a straight-line distance to the nearest woodland in OpenStreetMap, not a forest edge fixed by the forestry authority. Whether a setback applies in North Rhine-Westphalia is left open; the page advises asking the forestry authority before building.
Checklist to print
- □ Municipality, in writing: zoning plan, built-up area or outer area
- □ Lower forestry authority: is it forest, where is the edge, does a setback apply
- □ Forest on the plot: get conversion, compensation and levy quoted in writing
- □ Existing house: building file from the seller; building authority confirms lawful existence and permitted use
- □ Forestry land in the sale: ask the notary about approval under the GrdstVG (ASVG in Baden-Württemberg)
- □ Land register section II: easements on falling trees or rights of way
- □ Access: public road or secured access, not just a forest track
- □ Planned new build or extension: pre-application before you buy
For one parcel, our report gives the distance to the nearest woodland mapped in OpenStreetMap and protected-area and planning data where the state publishes it, and flags what is missing. It does not replace the forestry authority's answer or include the land register or the building-encumbrance register. Order a check before you buy.
Editorial team: GrundCheck. Checked: 12 November 2026.
Official sources, accessed 12 November 2026
- Section 2 BWaldG: definition of forest
- Section 9 BWaldG: forest conservation and conversion
- Section 29 BauGB: definition of a project
- Section 35 BauGB: building in the outer area
- Section 873 BGB: agreement and registration
- Section 1 GrdstVG: scope
- Section 2 GrdstVG: approval of sales
- Section 4 GrdstVG: cases without approval
- Baden-Württemberg agricultural structure act (ASVG), s. 1
- Baden-Württemberg building code, s. 4
- Baden-Württemberg forest act, s. 9
- Bavarian forest act, Art. 9 and 39
- Bavarian building code
- Berlin forest act, s. 6
- Brandenburg forest act, ss. 8 and 23
- Hamburg forest act, s. 4
- Hesse forest act, s. 12
- Mecklenburg-Vorpommern forest act, ss. 15 and 20
- Rhineland-Palatinate forest act, s. 14
- Saarland forest act, ss. 8 and 14
- Saxony forest act, ss. 8 and 25
- Saxony-Anhalt forest act, s. 8
- Schleswig-Holstein forest act, ss. 9 and 24
- Thuringia forest act, ss. 10 and 26